The Civil Engineering and Development Department signed a contract with Build King - SCT Joint Venture for the Contract No. NL/2017/03 Tung Chung New Town Extension - Reclamation and Advance Works.
Click here to Press Release
The Civil Engineering and Development Department signed a contract with Build King - SCT Joint Venture for the Contract No. NL/2017/03 Tung Chung New Town Extension - Reclamation and Advance Works.
Click here to Press Release
On 18 December 2017, the Islands District Council was briefed on the latest implementation progress of the TCNTE project including the proposed road works and infrastructure works in Tung Chung East and Tung Chung West, and the proposed ecological conservation measures in Tung Chung West.
Click here for Paper No.131/2017.
The Finance Committee of the Legislative Council approved the funding application for the construction of reclamation and advance works of Tung Chung New Town Extension.
Click here for Legislative Council Paper No. FCR(2017-18)15A
Gazette of Ma Wan Chung sewerage works were published on 8 September 2017 under Roads (Works, Use and Compensation) Ordinance (Chapter 370) as applied by section 26 of the Water Pollution Control (Sewerage) Regulation (Chapter 358, Sub. Leg.).
Click here for Gazette Notice
Gazette of Ma Wan Chung roadworks were published on 6 September 2017 under Roads (Works, Use and Compensation) Ordinance (Chapter 370).
Click here for Gazette Notice and Plan
The Civil Engineering and Development Department signed a contract with DrilTech Ground Engineering Limited for Contract No. NL/2017/02 – Tung Chung New Town Extension (West) - Site Investigation Works.
On 26 June 2017, the Islands District Council was briefed on the latest implementation programme of the Tung Chung New Town Extension (TCNTE) Project including statutory procedures, site investigation (SI), proposed reclamation and infrastructure works and the proposed works in Tung Chung Area 6, Ma Wan Chung, Tung Chung Valley and Tung Chung Stream.
Click here for Paper No.54/2017.
The approved draft Tung Chung Town Centre Area (TCTC) and Tung Chung Valley (TCV) Outline Zoning Plans (OZPs) were exhibited for public inspection on 17 February 2017.
The Chief Executive-in-Council approved the draft Tung Chung Town Centre Area (TCTC) and Tung Chung Valley (TCV) Outline Zoning Plans (OZPs) on 7 February 2017.
The Civil Engineering and Development Department signed a contract with Geotechnics & Concrete Engineering (Hong Kong) Ltd for the Contract No. NL/2016/01 – Tung Chung New Town Extension – Site Investigation Works Stage 1.
On 24 October 2016, the Islands District Council was briefed on the latest progress of the TCNTE project including statutory procedures, detailed design, site investigation works, infrastructure works for Tung Chung Area 58, establishment of community liaison center and reclamation works at Tung Chung East.
Click here for Paper No.109/2016 and Islands DC Meeting Minutes(24 October 2016)(Chinese Only)
The hearing of the Tung Chung Outline Zoning Plans (OZPs) were held on 4 October 2016.
The hearing of the Tung Chung Outline Zoning Plans (OZPs) were held on 29 September 2016.
The hearing of the Tung Chung Outline Zoning Plans (OZPs) were held on 28 September 2016.
Detailed design of infrastructure works for Tung Chung West for implementation of TCNTE commenced after appointment of design and construction consultants in September 2016.
The Environmental Permit (Permit No. EP-519/2016) for Tung Chung New Town Extension was granted by the Director of Environmental Protection. For details, please go to the Environmental Protection Department website.
Click here for permit
Detailed design of infrastructure works for Tung Chung East for implementation of TCNTE commenced after appointment of design and construction consultants in June 2016.
The Finance Committee of the Legislative Council approved the funding application for engaging consultants to undertake the detailed design and site investigation works for the implementation of Tung Chung New Town Extension - Design and Construction.
The Environmental Impact Assessment Report for Tung Chung New Town Extension (AEIAR-196/2016) was approved by the Director of Environmental Protection with conditions.
Click here for EIA Report
The Islands District Council (IsDC) was consulted on 1 February 2016 on the draft Outline Zoning Plans (OZPs).
The Tung Chung Rural Committee (RC) was consulted on 28 January 2016 on the draft Outline Zoning Plans (OZPs).
The proposed undertaking and the foreshore and sea-bed to be affected were gazetted on 8 January 2016 under Foreshore and Sea-bed (Reclamations) Ordinance (Chapter 127).
Click here for Foreshore and Seabed Gazette Notice and Plan (Plan No. ISM2583b)
The draft Tung Chung Extension Area, Tung Chung Town Centre Area (TCTC) and Tung Chung Valley (TCV) Outline Zoning Plans (OZPs) were gazetted on 8 January 2016 under the Town Planning Ordinance (Chapter 131).
Click here to Statutory Planning Portal 2
Carried out 3-stages public engagement activities.